The short version
Almost everything binding on the AI build-out is physical: electrons that are under contract but not flowing, racks whose power draw is outrunning the buildings around them, queues and transformer lead times, and a wafer stage nobody has managed to reshore. I have put fourteen dated predictions on those constraints, with outside sources holding the answer key.
What I'm sure of
The constraint on AI is moving from chips to the grid, and the industry talking about it is mostly not the industry that has to build it.
What I'm not
How fast any of it clears. That is what the dates below are for — I would rather be scored than believed.
The flash test
Every module we build gets one burst of artificial sunlight before it is allowed out of the building. A fraction of a second under the simulator, and the machine writes down what that specific panel actually does — not what the datasheet promises, not what I hoped it would do the day we commissioned the line.
If it comes in under spec, it does not ship. There is no version of that conversation where I explain to a flash tester that the module is directionally fine. The instrument does not know who owns the factory and would not care.
Twenty-three years in energy and I have never once watched a forecast go through anything like that. So before I tell you what I think is about to happen, here is the standard I am willing to be held to: every claim below has a date, a number, and someone outside this company who publishes the answer.
Experience is a nameplate rating. Calibration is measured output.
What's actually binding
The AI build-out gets discussed as a chip story and a capital story. From where I sit it is neither. Four things are binding, all of them physical, and the people writing about AI are mostly not the people who have to pour the concrete.
Contracted is not delivered
About 6.7 GW of nuclear is now under contract to hyperscalers — Microsoft at Crane, Meta at Clinton, Amazon at Susquehanna, Google at Duane Arnold, Meta again at Perry and Davis-Besse. It is the most quoted number in the AI-energy conversation.
One of those plants is actually delivering. Susquehanna was already running. Crane and Duane Arnold are restarts and both are still shut down; Duane Arnold is not expected on the grid until the first quarter of 2029. Contracting takes a signature. Delivering takes restart licences, fuel, staff, and an interconnection, all on nuclear timelines.
Contracting is a press release. Delivering is a decade.
The rack is outrunning the building
A GB300 NVL72 rack draws up to 142 kW today. Vera Rubin is reported at roughly 180–220 kW for the second half of 2026. NVIDIA's own roadmap puts Rubin Ultra at around 600 kW on 800 V DC in 2027. A megawatt rack is one generation past anything published.
Power density is the variable that quietly rewrites everything downstream of it — cooling, switchgear, floor loading, interconnection, and the entire economic case for putting generation on the same site as the load. It is the number I watch most closely and the one I almost never see discussed outside a data-centre engineering meeting.
The unglamorous layer
If I am wrong about all fourteen predictions at once, this is how. The binding constraint on AI turns out to be neither chips nor capital nor models, but interconnection queues and transformer lead times — the physical layer nobody writes essays about because there is no curve to draw.
It is also the least glamorous thing to be right about, which is roughly how you can tell it matters. Every forecast in this document, including mine, assumes the electrons show up on schedule.
Everyone reshores the easy end
China holds roughly 95–97% of global solar wafer capacity and 93% of polysilicon. Wafer is the hardest stage — the most capital-intensive, the most energy-intensive, and the one with the least Western activity. It is also the one that reshoring announcements quietly skip.
Module assembly is cheap and fast to stand up, so that is where the ribbon-cuttings are. Cells are harder. Wafer is where you find out whether industrial policy actually worked, and we are not close.
Everyone starts at the assembly end, because it's the end that photographs well.
So I put dates on it
Those four arguments are worth exactly nothing if I never have to answer for them. So here they are as fourteen predictions, each with a deadline, a confidence, and a named public source that settles it — EIA, IEA, LBNL, the NRC record, SEIA and Wood Mackenzie, ITRPV, published price lists. None of them work for me, which is the entire point.
Horizontal: the year each row comes due · Vertical: how confident I am
| # | Prediction | By when | Confidence | Resolved by |
|---|---|---|---|---|
| 1 | Crane Clean Energy Center (Three Mile Island Unit 1) delivers power to the grid under its Microsoft PPA | By whenEOY 2027 | Confidence55%55% Confidence | Resolved byEIA-860M; Constellation filings |
| 2 | TSMC produces N3-class logic in volume production at its Arizona campus | By whenEOY 2027 | Confidence55%55% Confidence | Resolved byTSMC quarterly disclosure |
| 3 | A frontier-class model — top-3 on a public head-to-head leaderboard at time of measurement — is priced below $0.10 per million input tokens at standard-tier, uncached, non-batch list price | By whenEOY 2028 | Confidence60%60% Confidence | Resolved byPublished provider price lists |
| 4 | A single buyer deploys more than 1,000 humanoid robots in revenue-generating production work | By whenEOY 2029 | Confidence45%45% Confidence | Resolved byBuyer or maker disclosure; audited customer statement |
| 5 | A production AI compute rack above 1 MW is deployed commercially | By whenEOY 2029 | Confidence45%45% Confidence | Resolved byVendor or operator spec disclosure |
| 6 | At least 4 GW of US nuclear capacity is physically delivering power under data-center PPAs | By whenEOY 2029 | Confidence40%40% Confidence | Resolved byEIA-860; PPA counterparty filings |
| 7 | Solar is the single largest source of new US generating capacity in every year from 2023 through 2029 | By whenEOY 2029 | Confidence65%65% Confidence | Resolved byEIA Electric Power Monthly |
| 8 | A perovskite-silicon tandem module ships commercially at >28% module efficiency with >500 MW cumulative shipped | By whenEOY 2029 | Confidence40%40% Confidence | Resolved byThird-party certification + manufacturer shipment disclosure |
| 9 | US-made silicon solar cells supply >20% of US module assembly output | By whenCY 2029 | Confidence50%50% Confidence | Resolved bySEIA / Wood Mackenzie Solar Market Insight |
| 10 | US data centers exceed 13% of total US electricity consumption | By whenCY 2030 | Confidence45%45% Confidence | Resolved byLBNL Data Center Energy Usage Report |
| 11 | Global data centre electricity demand exceeds 900 TWh | By whenCY 2030 | Confidence70%70% Confidence | Resolved byIEA |
| 12 | A commercial SMR reaches grid-connected commercial operation in the US | By whenEOY 2030 | Confidence45%45% Confidence | Resolved byNRC licensing record; EIA-860 |
| 13 | Tandem modules exceed 5% of global module shipments | By whenCY 2030 | Confidence30%30% Confidence | Resolved byITRPV; CPIA |
| 14 | China's share of global solar wafer capacity falls below 90% | By whenEOY 2030 | Confidence35%35% Confidence | Resolved byIEA; BloombergNEF |
How this gets scored
A full public pass every January, starting January 2028, when the first two rows come due. A row is right only if its exact numeric condition is met by the named resolver. No partial credit, no close enough, no swapping in a friendlier source later.
A row enters the score only after its deadline passes, even when it is obviously settled early — otherwise the good news lands while the bad news is still open, and every interim number flatters me. If a resolver stops publishing, the row scores Wrong rather than getting quietly removed.
I do not grade these. The resolvers do. My job every January is arithmetic, and arithmetic is checkable by anyone who disagrees with it.
Being wrong is the point, not the failure. A red row I argued hard for shows exactly where my model is broken, and that is worth more than ten green rows I hedged into safety.
The reasoning
1. Crane restarts on time — EOY 2027, 55%
Constellation received FERC approval in June 2026 and NRC approval of its fuel receipt and possession amendment on 1 July 2026, clearing the way for restart in the second half of 2027, with the reactivated operating license targeted for May 2027. The $1B DOE loan closed in November 2025 and roughly ninety operator candidates are in the licensing pipeline. The binding constraint here is not reactor hardware — it is regulatory sequencing and staffing a plant that has been dark since 2019.
I'm at 55% rather than 75% because “delivers power to the grid” is a harder line than “on schedule,” and because every schedule in this industry has a hidden month in it. But this is the single most important row in the register: it is the first megawatt of the entire AI-nuclear story to actually show up. Everything else in that trade is paper.
2. TSMC hits N3 in Arizona — EOY 2027, 55%
TSMC's own guidance puts Fab 2 at N3 volume production in the second half of 2027, and on its Q4 2025 call it said it was pulling that schedule forward. Taiwanese press reports — not TSMC guidance — add that equipment installation is running early and that US capacity is fully booked; I treat those as unconfirmed, and TSMC's fourth Arizona fab only began construction in early 2026. I am betting that TSMC hits its own published date, which sounds trivial and is not — leading-edge node transitions on new soil with a new workforce slip as a matter of routine.
Note what this row deliberately excludes. Intel is already running 18A in volume at Fab 52 in Arizona, so “leading-edge logic in volume on US soil” is a question that has already been answered. The open question is specifically whether TSMC can replicate Taiwan's ramp discipline in Arizona, which is the one that matters for supply-chain resilience.
3. Frontier inference below $0.10 per million input tokens — EOY 2028, 60%
GPT-4 launched in March 2023 at $30 per million input tokens. Today the cheapest credibly frontier-adjacent model publishes $0.22 per million for off-peak cache-miss input, rising to $0.44 at peak. That is roughly a 140x decline in three and a half years, and the mechanism — better hardware utilization, distillation, brutal competition among a half-dozen labs — has not run out.
The wording here is doing a lot of work, and deliberately. Cached input runs far below the standard rate — OpenAI lists $0.005 per million on its smallest tier — and batch tiers cut it further, so on a loose reading this resolved a year ago. Legacy small models already sit at or below $0.10. The bet is specifically that a model people would call frontier — top-3 in public head-to-head ranking at the moment of measurement, not a cheap tier a generation behind — lands under a dime at standard list price. The risk is that “frontier” keeps running away from the price curve, which is exactly what it has done so far.
4. Humanoids doing paid production work at scale — EOY 2029, 45%
UBTech's FY2025 results put full-size humanoid sales at 1,079 units in 2025 alone, across BYD, Geely, FAW-VW, Dongfeng and Foxconn — but no single buyer is close to a thousand. AgiBot announced its 15,000th unit in June 2026, which is a manufacturing milestone rather than a deployment number; Omdia's independent count of its 2025 shipments was 5,168. Tesla's Optimus, per Musk on the January 2026 earnings call, is not in material use in Tesla's own factories.
So the industry has cleared the pilot bar convincingly and has not cleared the fleet bar at all. I'm at 45% because the gap between an impressive pilot and a thousand-unit fleet that pays for itself is precisely where robotics has disappointed for forty years. This row says deployed and doing revenue work, not ordered — order announcements in this sector are marketing.
5. A 1 MW rack — EOY 2029, 45%
GB300 NVL72 racks draw up to 142 kW today. Vera Rubin is reported at roughly 180–220 kW for the second half of 2026. NVIDIA's GTC 2025 roadmap put Rubin Ultra NVL576 at roughly 600 kW on 800 V DC for the second half of 2027 — a figure from the roadmap presentation rather than a published spec sheet.
A megawatt rack is therefore not on the published roadmap — it is one generation past it. I'm betting the roadmap keeps its slope through 2029. This is the row I care about most professionally, because rack density is the variable that quietly rewrites everything downstream: cooling, switchgear, floor loading, interconnection, and the entire economic case for putting generation on the same site as the load.
Power density is the real story of AI infrastructure and almost nobody outside the industry is tracking it.
6. Four gigawatts of nuclear actually delivering — EOY 2029, 40%
About 6.7 GW of existing-fleet and restart nuclear is now under contract to hyperscalers: Microsoft/Crane at 835 MW, Meta/Clinton at 1,121 MW, Amazon/Susquehanna at 1,920 MW, Google/Duane Arnold at 615 MW, and Meta/Vistra at 2,176 MW across Perry and Davis-Besse. Amazon's Comanche Peak agreement adds up to 1,200 MW more. I state the sum rather than a round number because no published aggregate survives checking.
Restarted megawatts delivered today: zero. Susquehanna is already delivering under the Amazon contract and the Vistra volumes begin in late 2026, so power does flow under some of these PPAs — but every megawatt of it comes from a plant that was already running. Crane and Duane Arnold, the two restarts, are both still shut down, and Duane Arnold is not expected on the grid until the first quarter of 2029.
That gap is the entire point of this row. Contracting is a press release. Delivering requires restart licenses, uprate approvals, fuel, staff and interconnection, all on nuclear timelines. And note what the numbers do to my own confidence here: with Susquehanna flowing and Vistra starting, the 4 GW bar may well clear on plants that never shut down, long before a single restart contributes. If this row resolves true that way, it resolves true for reasons that have nothing to do with the thesis underneath it — so I am saying that now rather than claiming the win later.
7. Solar wins new capacity seven years running — EOY 2029, 65%
Solar was 53% of US capacity additions in 2023, 66% in 2024, and 54% in 2025 — the largest single source each year, five consecutive years by SEIA's count. EIA projects roughly 51% of utility-scale additions in 2026 against record total additions of about 86 GW.
Three of the seven years are banked and 2026 is tracking. The bet is really about 2027, 2028 and 2029, and the risk is not solar's cost curve — it is a policy shock or a gas-turbine resurgence for data-center baseload. Note what actually drove the 2024-to-2025 dip from 66% to 54%: storage grew faster and solar shrank. SEIA and Wood Mackenzie put 2025 installations at 43.2 GW, down 14% year on year. Solar kept the crown on a falling volume, which is a weaker position than the share number alone suggests.
8. A real tandem module at commercial volume — EOY 2029, 40%
The efficiency question is closer to settled than most people realize. Trina certified a full-size, industrial-format tandem module at 29.2% and 907 W with TÜV SÜD in June 2026, and LONGi's certified tandem cell record is now 35.5%. The record is not the problem.
Volume is the problem. The largest publicly disclosed commercial tandem order is 1.2 MW — GCL's win for a Huaneng research institute in March 2026, the first publicly tendered tandem order from one of China's five major state generators. Trina has separately announced a commercial tandem order deployed in New Zealand without disclosing volume, so I cannot rule out something larger. GCL's Kunshan line is nameplated at 1 GW; my own read is that realistic output is 100 MW-class, which is an industry estimate rather than a published figure. LONGi's tandem line is a 100 MW pilot, and Trina's investor communications put commercial tandem shipments at scale in 2028–2029.
So I've set the bar where the actual uncertainty lives: 500 MW cumulative shipped at above 28%. That requires someone to solve encapsulation and field durability at scale, not to win another certification. Perovskite stability under real-world stress remains the open question, and it is a materials-science problem, not a manufacturing one.
9. US cells reach 20% of US module output — CY 2029, 50%
The US has built enormous module assembly capacity — 65 to 70 GW nameplate — on top of almost no domestic cell production. SEIA's last published operating figure is 3 GW of cell capacity. Against the 31 to 37 GW of modules the US actually manufactured over the past year, that is roughly 8 to 9%.
Read that number carefully, because a competing one is circulating. PV Tech puts domestic cell coverage at one-third to just over 40% by comparing crystalline cell capacity against crystalline module capacity. I am using operating cell output against actual module output, which is the stricter basis and the one this row resolves on. The ramp itself is real: ES Foundry completed its expansion to 3 GW in July 2026, Qcells Cartersville began cell production in June 2026 and is ramping toward 3.3 GW, Suniva and Silfab add another 2 GW, Canadian Solar's CS PowerTech opened in Indiana in July 2026 with over 6 GW at full buildout, and T1 Energy starts by end-2026. That is roughly 10 GW operating or ramping.
This is a coin flip, and I have specified the denominator as assembly output rather than nameplate capacity, because that distinction is where most published claims about domestic content quietly cheat. Cell manufacturing is genuinely harder to stand up than assembly — it is a chemistry and yield problem, not a bolting-together problem — and more announced cell lines get cancelled than commissioned.
10. US data centers past 13% of national electricity — CY 2030, 45%
LBNL's 2025 Update puts 2024 at 192 TWh, or 4.7% of US electricity, with a 2030 reference case of 649 TWh — about 11.8% — inside a range of 9.5% to 15.3%, or 521 to 843 TWh. Worth knowing if you are grading me against it: that same update revised its own history downward, on reduced reported GPU shipments for 2023 and 2024. The resolver's baseline moves too.
Thirteen percent is above the reference case and below the high case. I am betting the over, because load is contracted years ahead, capex is already committed, and the historical pattern in this specific series has been that LBNL revises upward. The risk is that efficiency gains outrun deployment, or that interconnection — not capital, not chips — becomes the binding constraint. That second one is underrated and it is the same queue problem that governs row 7.
11. Global data centre demand past 900 TWh — CY 2030, 70%
The IEA's April 2026 update estimates 2025 at roughly 485 TWh — its own modelled figure rather than a measured actual — with overall data centre demand up 17% in the year and AI-focused facilities up about 50%.
Nine hundred is a deliberately slightly-below-central line, which is why this is one of my higher confidences. Worth noting: the IEA's 2030 projection barely moved between April 2025 and April 2026. The prose of the newer report says around 950 TWh while its own Annex A base case table still gives 945 — the identical figure to a year earlier. So the modelled output is essentially unchanged despite a full year of enormous announcements. Either the model is insensitive to news or the announcements are mostly re-sequencing the same buildout. I lean toward the second, and that is a mildly deflationary read on the whole sector.
12. First US commercial SMR on the grid — EOY 2030, 45%
Zero SMRs operate in the US today. Oklo broke ground at Idaho National Lab in September 2025, is proceeding via the DOE authorization pathway rather than NRC licensing, has cleared two of five DOE gates as of June 2026, and has moved its own language from a late-2027-to-early-2028 window to 2028. TVA's Clinch River BWRX-300 is furthest along the NRC route, with the safety analysis report accepted in July 2025 and no construction permit yet issued.
The definitional trap matters here: Aurora at INL is a DOE-authorized demonstration, so even at startup it may not count as grid-connected commercial operation. I've pushed my date to 2030 and sit just below a coin flip. The regulatory path is genuinely accelerating and nuclear timelines genuinely slip, and I don't think either force clearly dominates.
13. Tandems take 5% of global shipments — CY 2030, 30%
TOPCon accounted for more than 94% of module shipments among the top ten manufacturers in the first half of 2025, against roughly 706 GW shipped globally. The 88.3% figure that circulates is cell shipments among the top five — a different measure, and one worth keeping separate. Tandem is under half a percent on any of these bases. ITRPV's roadmap puts silicon tandem above 17% only by 2036, which implies well under 5% at 2030.
I am betting against the published roadmap, which is why this is my lowest confidence and one of only two rows where I'm taking a genuinely contrarian position. Tandems must beat TOPCon on delivered dollars per watt, not on efficiency, and Chinese TOPCon overcapacity keeps that floor on the ground through roughly 2032. If I'm right, learning curves cracked an entrenched incumbent faster than the industry's own consensus expected. If I'm wrong, incumbency in commodity manufacturing is even more durable than I already think it is — and that has implications well beyond solar.
14. The first crack in China's wafer monopoly — EOY 2030, 35%
China holds roughly 95–97% of global solar wafer capacity and 93% of polysilicon. On modules, IEA-PVPS puts it at 86.4% of production against 83% of capacity — worth separating, because production share and capacity share are not the same claim. Wafer is the hardest stage — the most capital-intensive, the most energy-intensive, and the one with the least Western activity.
Note how easy it would be to make this row unlosable. Betting that China still holds most of global module capacity in 2030 is not a prediction, it is a description. Betting on wafer share dropping below 90% is a real bet: it requires meaningful non-Chinese ingot and wafer capacity to be built and operated, not announced. Everyone reshoring solar starts at the assembly end because it is cheap and fast.
Wafer is where you find out whether industrial policy actually worked.
Where I'm most likely wrong
The ones I'd bet the house on are the boring ones: row 7 (solar keeps winning new capacity), row 11 (global data center demand), row 3 (token prices keep collapsing). These aren't really predictions, they're extrapolations of curves that are already moving and already funded. If I'm wrong on those I've misread something structural and I want to know fast.
The ones that scare me are rows 8 and 13 — tandems, at both the volume bar and the market-share bar — and row 4, humanoids at fleet scale. My whole thesis leans on learning curves eventually cracking every incumbent, and on intelligence becoming embodied in manufacturing. If TOPCon just keeps winning on price through 2030 and humanoids stay stuck in pilot purgatory, then the flywheel is slower and lumpier than I've been telling people, and the “intelligence reshapes the physical economy” leg is more aspiration than trend.
And row 6 sits underneath all of it. About 6.7 GW of nuclear is contracted to AI, and the only plant actually delivering under those contracts today is Susquehanna. Every forecast in this document assumes the rest of the electrons show up. The most likely way I'm wrong about all fourteen rows at once is that the binding constraint on AI turns out to be neither chips nor capital nor models, but interconnection queues and transformer lead times — the unglamorous physical layer that nobody writes essays about because there's no curve to draw.
Disclosure
I run a domestic solar module manufacturer. Rows 7, 8, 9, 13 and 14 sit in my industry, and rows 9 and 14 describe conditions my company would benefit from. Read them as informed and interested — I have better information than most analysts writing about this supply chain, and I also have a position. The register format is partly a discipline against my own book.
Published September 2026. Fourteen rows open. First scoring pass: January 2028.
Sources
- U.S. Department of Energy, Office of Energy Dominance FinancingCrane Restart
- American Nuclear Society (Nuclear Newswire)Second-quarter updates from Constellation: New PPAs, Crane restart, and more
- Constellation EnergyConstellation to Launch Crane Clean Energy Center, Restoring Jobs and Carbon-Free Power to The Grid
- Constellation EnergyConstellation, Meta Sign 20-Year Deal for Clean, Reliable Nuclear Energy in Illinois
- U.S. Securities and Exchange Commission (Talen Energy Corp. Form 8-K exhibit)Talen Energy Expands Nuclear Energy Relationship with Amazon (Form 8-K, Exhibit 99.1, June 11, 2025)
- NextEra EnergyNextEra Energy and Google Announce New Collaboration to Accelerate Nuclear Energy Deployment in the U.S.
- Vistra Corp. (via PR Newswire)Vistra and Meta Announce Agreements to Support Nuclear Plants in PJM and Add New Nuclear Generation to the Grid
- U.S. Nuclear Regulatory CommissionClinch River Nuclear Site Application
- U.S. Energy Information AdministrationAnnual Electric Power Industry Report, Form EIA-860 detailed data with previous form data (EIA-860A/860B)
- U.S. Energy Information AdministrationPreliminary Monthly Electric Generator Inventory (based on Form EIA-860M as a supplement to Form EIA-860)
- TSMC (Taiwan Semiconductor Manufacturing Company)TSMC Arizona
- TSMC Investor Relations (LSEG edited transcript, Q4 2025 earnings call, January 2026)Q4 2025 Taiwan Semiconductor Manufacturing Co Ltd Earnings Call (Chinese, English) on January 15, 2026 / 6:00AM
- TrendForce[News] TSMC Reportedly Eyes 2H27 3nm Mass Production at Arizona Fab 2; Four U.S. Fabs Said to Be Fully Booked
- TrendForce[News] TSMC Reportedly Accelerates Arizona 2nd Fab, Eyes 3Q26 Tool Install, 2027 3nm Production
- U.S. Securities and Exchange Commission (Intel Corp Form 8-K, Q3 2025 earnings release, 23 October 2025)Intel Reports Third-Quarter 2025 Financial Results
- U.S. Securities and Exchange Commission (Intel Corp Form 8-K, Q4 2025 earnings release)Intel Reports Fourth-Quarter and Full-Year 2025 Financial Results
- Intel Corporation (CEO/CFO comments, Q2 2026 earnings call, 23 July 2026)CEO/CFO Earnings Call Comments — Comments from CEO Lip-Bu Tan and CFO Dave Zinsner
- U.S. Securities and Exchange Commission (Intel Corp Form 8-K, Q2 2026 earnings release, 23 July 2026)Intel Reports Second-Quarter 2026 Financial Results
- TechCrunchOpenAI releases GPT-4, a multimodal AI that it claims is state-of-the-art
- OpenAIPricing | OpenAI API
- GoogleGemini Developer API pricing
- AnthropicPlans & Pricing | Claude by Anthropic
- Arena (formerly LMArena / LMSYS Chatbot Arena)LLM Leaderboard - Best Text & Chat AI Models Compared
- xAIModels | xAI Docs
- DeepSeekModels & Pricing — DeepSeek API Docs
- Interesting EngineeringVideo: China's humanoid robot dances and kicks box as Walker S2 hits 1,000 units
- AGIBOT (company newsroom)AGIBOT Reaches 10,000 Units as Real-World Demand for Robots Accelerates
- ElectrekMusk admits no Optimus robots are doing 'useful work' at Tesla — after claiming otherwise
- NVIDIA (docs.nvidia.com, Enterprise Reference Architectures)System Hardware & Components — NVIDIA NVL72 AI Factory
- Lenovo PressLenovo NVIDIA GB300 NVL72 Rack Scale AI Product Guide
- Data Center FrontierNVIDIA GTC 2025 Unveils Revolutionary Chips, Systems, and Optical Networking for Hyperscale AI Data Centers
- NVIDIA NewsroomNVIDIA Vera Rubin Ramps Into Full Production to Power Agentic AI Factories Worldwide
- SemiAnalysisVera Rubin – Extreme Co-Design: An Evolution from Grace Blackwell Oberon — SemiAnalysis, 25 February 2026 (Wega Chu, Dylan Patel, Daniel Nishball et al.)
- U.S. Energy Information AdministrationNew U.S. electric generating capacity expected to reach a record high in 2026 (Today in Energy, U.S. Energy Information Administration, February 20, 2026)
- Wood Mackenzie (co-publisher of the SEIA/WoodMac Solar Market Insight report)U.S. Adds 43 GW of New Solar Capacity in 2025, Marking Fifth Straight Year as Top Source of New Power
- pv magazineUS solar installations reach 43 GW in 2025 despite slowdown
- Utility DiveUS deployed a record 32 GW of solar generating capacity in 2023: SEIA
- Solar Now (syndicated mirror of the SEIA Solar Market Insight 2024 Year in Review page)Solar Market Insight Report 2024 Year in Review – seia.org
- pv magazineES Foundry completes 3 GW solar cell factory expansion
- Canary MediaNew Qcells plant doubles current US capacity to make solar cells
- PV TechT1 Energy begins construction at 2.1GW TOPCon cell manufacturing facility in Texas
- PV TechPart 2: Mapping the gaps in the US solar supply chain – from polysilicon to modules
- pv magazine InternationalCanadian Solar subsidiary opens 6 GW solar cell factory in Indiana
- Trina Solar (Trinasolar)Trinasolar achieves 907W power output for its tandem modules, setting a new world record
- pv magazine GlobalTrina Solar announces 907 W tandem solar module with 29.2% efficiency
- LONGi Green Energy Technology35.5%! LONGi Once Again Breaks World Record for Crystalline Silicon-Perovskite Tandem Solar Cell Efficiency
- pv magazine GlobalGCL Optoelectronics wins China's first commercial perovskite-silicon tandem PV module order
- GCL Technology Holdings LimitedGCL Photovoltaic's GW-Scale Perovskite Industrial Base Officially Commences Production in Kunshan
- Perovskite-InfoLONGi to build 100 MW silicon-perovskite tandem pilot production line in Shaanxi
- TaiyangNewsITRPV Sees PV Shipments Stabilize At 706 GW In 2025
- pv magazine InternationalJinko edges past Longi in first-half solar shipments as TOPCon dominates
- pv magazine International (reporting IEA-PVPS Trends in PV Applications 2025)Thirty-five countries now operate GW-scale annual PV markets
- pv magazine Global (reporting Bernreuter Research)China dominates global polysilicon capacity, says Bernreuter Research
- VDMAInternational Technology Roadmap for Photovoltaic (ITRPV)
- China Photovoltaic Industry Association (CPIA)About Us — China Photovoltaic Industry Association (CPIA)
- Lawrence Berkeley National Laboratory (Energy Analysis Division), hosted on UC eScholarshipUnited States Data Center Energy Usage Report: 2025 Update (Smith, Hubbard, Newkirk, Ganeshalingam, Holecek, Sartor, Mills, Shehabi — Energy Analysis Division, Lawrence Berkeley National Laboratory, June 2026)
- Lawrence Berkeley National Laboratory — Center of Expertise for Data Center EnergySector-Wide Modeling & Forecasting
- International Energy Agency (IEA's own asset CDN)Key Questions on Energy and AI — World Energy Outlook Special Report (International Energy Agency, April 2026)
- International Energy Agency (IEA's own asset CDN)Energy and AI — World Energy Outlook Special Report (International Energy Agency, April 2025)
- Counterpoint ResearchGenAI Smartphone Share to Rise to 45% of Global Shipments in 2026 (Tarun Pathak and Karn Chauhan, Counterpoint Research, 22 June 2026)
Every figure above was checked against a primary source before publication. Where a number is my own estimate rather than a published figure, it says so.